Current Setup(tower in progress):
Digging the hole for my 12m Tower!
back-yard.JPG
back-yard2.JPG
Making the cement base:
The Cage keeping cement together:
1cage.jpg
Welding a X on the Bolts holding the tower up so they do not pull out of the cement:
2bolts-welded.JPG
Soldering earthing cable to cage as the cabe needs to be part of the earthing (soldering earth cable to earth spike):
3busy-soldering.JPG
4wire-soldered.JPG
5cage-in-ground.JPG
Cage and earthing done getting ready to start mixing:
6cage-finel-prep_N_.
The result of 0.6 cube stone, 0.6 cube Sand and 8.5 Bags of cement mixed and put in a hole in the Ground:
7final-cement-base.J
Here are pics of the T-Pice that is used to pull the tower up and down;
1base-swivel.JPG
2tower--on-ground.JP
3tower-up-on-its-way
4tower-up-bolts1.JPG
5tower-up-bolts2.JPG
- -)